The task at hand now is to (56) the progra

题型:单项选择题

问题:

The task at hand now is to (56) the programmers who still use yesterday’s software technology to solve today’s software problems. Object-oriented programming requires a new attitude toward problem (57) . Problem (57) with computer system becomes more natural. Application can (58) be translated into (59) . Although it is commonly believed that it will be easier to train new programmers to use object-oriented techniques than to (60) programmers who have substantial experience in applying conventional programming language constructs.

(57)是()

A.solve

B.solves

C.solved

D.solving

考点:计算机软件水平考试高级系统分析师系统分析师
题型:单项选择题

解方程(4′×2=8′)

(1)5x(x+3)=2(x+3)                 (2)3x2-6x+2=0

题型:单项选择题

有60枝百合花,每8枝扎成一束。可以扎几束花?还余几枝?

题型:单项选择题


某建筑公司(乙方)于某年6月20日与某企业(甲方)签订了修建建筑面积为3000m2工业厂房的施工合同。乙方编制的施工方案和进度计划已获工程师批准。该工程的基坑开挖土方量为4500m3,假设工料单价为4.2元/m2,综合费率为直接费的20%。该基坑施工方案规定,土方工程采用租赁一台斗容量为反1m3反铲挖掘机施工(租赁费为450元/台班)。甲、乙双方合同约定7月11日开工,7月20日完工。在实际施工中发生了如下事件。
事件1:因乙方租赁的挖掘机大修,晚开工2天,造成人员窝工10个工日。
事件2:施工工程中,因遇软土层,接到工程师7月15日停工的指令,进行地质复查,配合用工15个工日。
事件3:7月19日接到工程师于7月20日复工指令,同时接到基坑开挖深度加大2m的设计变更通知单,由此增加土方开挖量900m3
事件4:7月20日至7月22日,因降罕见暴雨迫使基坑开挖暂停,造成人员窝工10个工日。
事件5:7月23日用30个工日修复冲坏的永久道路,7月24日恢复挖掘工作,最终基坑于7月30日挖掘完毕。
[问题]

建筑公司对上述哪些事件可以向甲方提出索赔哪些事件不可以向甲方提出索赔说明理由。

题型:单项选择题

有两个关系R和S,分别包含15个和10个元组,则在R∪S,R-S,R∩S中不可能出现的元组数目情况是

A.15,5,10

B.18,17,7

C.21,11,4

D.25,15,0

题型:单项选择题

局域网中常用的介质访问控制方法有: 【1】 、令牌总线(Token Bus)、令牌环 (Token Ring)。

更多题库