The WBS,estimates for each work package,an
题型:单项选择题
问题:
The WBS,estimates for each work package,and the network diagram are completed.Which of the following would be the NEXT thing for the project manager to do ?()
A.Sequence the activitie
B.Verify that they have the correct scop
C.Create a preliminary schedule and get the team's approva
D.Complete risk managemen