The earned value technique is a commonly used method of performance measurement.It integrates project scop,schedule,and cost measures to help the project management team assess project performance.If aproject's Cost Performance Index(CPI=EV/AC) value less than 1.0,it means that______。

A.the cost savings for work completed
B.the project is ahead of its planned schedule
C.the cost overrun for work completed
D.less work was completed than was planned

考点:计算机软件水平考试高级信息系统项目管理师高级信息系统项目管理师上午试题