某混凝土工程,9月份计划工程量为5000m3,计划单价为400元/m3;而9月份实际

题型:单项选择题

问题:

某混凝土工程,9月份计划工程量为5000m3,计划单价为400元/m3;而9月份实际完成工程量为4000m3,实际单价为410元/m3,则该工程9月份的进度偏差为( )万元。

A.-36
B.36
C.40
D.41

考点:一级建造师建设工程项目管理建设工程项目管理
题型:单项选择题

坚持可知论的观点( )。

A.一定是唯物主义

B.一定是辩证法

C.可能是唯物主义

D.可能是唯心主义

题型:单项选择题

It is easy to find your way about in New York. It is laid out so regularly. Instead of streets winding and twisting (迂回) as they do in London, they are all regular and well planned. The streets running north and south are called “avenues” and are numbered, e.g. 1st Avenue, 2nd Avenue, etc. The streets going east and west are called “streets” and are also numbered, e.g. 51st Street, 63rd Street. It is all much more logical (合理的) than London’s street names. But I couldn’t help thinking how much more interesting than these dull cold numbers are London’s illogical but colorful names of streets, e.g. “Bishopgate” (which is not a gate and hasn’t a Bishop in it); “Haymarket” or “Corn market” (where you won’t see any hey or corn) or “Poultry” (without a living chicken anywhere in sight) or “Thread needle Street” (where you won’t find little girls learning to sew).

小题1:In the second sentence of the passage, “laid out” means ______.

A.built

B.be put

C.designed

D.cut down小题2:The streets running from north to south are called _______.

A.avenues in London

B.streets in America

C.avenues in New York

D.streets in London小题3:According to the writer’s opinion, ______.

A.avenues and streets are the same

B.streets in America are better than avenues in England

C.streets in New York are better than those in London

D.the writer didn’t agree with the London streets planners小题4:The names of streets both in London and New York ______.

A.are quite good

B.are interesting

C.are not practical

D.differ greatly in form小题5:The writer tells his readers that he prefers (更喜欢) _____.

A.London streets

B.New York streets

C.both

D.neither

题型:单项选择题

患者,女,18岁。春天郊游后出现红疹、全身瘙痒、皮肤水肿等过敏反应。应选用的药物是()

A.阿司匹林

B.氯苯那敏

C.雷尼替丁

D.毛果芸香碱

E.阿托品

题型:单项选择题

确定应收账款评估值的基本公式是;应收账款评估值=( )。

A.应收账款账面余额-已确定坏账损失-预计坏账损失

B.应收账款账面余额-坏账准备-预计坏账损失

C.应收账款账面余额-已确定坏账损失-坏账损失

D.应收账款账面余额-坏账准备-坏账损失

题型:单项选择题

造价工程师的()任务是合理确定并采取有效措施控制建设工程造价。

A.基本

B.根本

C.重要

D.主要