A projeet team budgeted US $3,000 for the
题型:单项选择题
问题:
A projeet team budgeted US $3,000 for the work performed and has spent US $4,000 to date. If they budgeted US $5, 000 for the work scheduled, what is the cost variance ?()
A.$-1,000.
B.$2,000.
C.$1,000.
D.$-2,000.