按IMF统计口径,国际收支平衡表中的进出口贸易额是按()进行统计的。 A.CIF B

题型:单项选择题

问题:

按IMF统计口径,国际收支平衡表中的进出口贸易额是按()进行统计的。

A.CIF

B.CFR

C.FOB

D.进口额按CIF

E.出口额按FOB

考点:经济学国际金融国际金融题库
题型:单项选择题

根据短文内容,用所给词的适当形式填空,使短文意思完整通顺。

     I'm a middle school student. I study at NO. 2 Middle School. I like l_____ (watch) TV very much. 

 I turn on (打开) TV first  when come back home after school every afternoon.  I like 2_____ (sport)

 shows best. I think they are exciting. I often watch a soccer game or a basketball game on TV.  

Sometimes I watch TV for many hours. My mother says," It's bad for your eyes. 3_____  (not watch) 

TV too much."  But I don't mind that. My sister, Mary, is a  4_____ (thirteen) girl. She loves music.

She often 5_____ (watch) music shows. She thinks it is  6_____  (relax).  7_____ (she) favorite music

 is pop music, and she loves English, too, so she enjoys  8_____ (sing) English songs. But she can't 

stand classical music (古典音乐). She thinks it's boring. My little cousin says she likes cartoons. People

 in the cartoons are always  9_____ (fun). They make children 10_____ (laugh).     

     In my opinion, different people like different shows. It's just like different people have their own

 hobbies. Some of us never watch TV!

题型:单项选择题

利用平方差公式计算99992

题型:单项选择题

(四)

背景资料

某机电安装工程项目开工之前,承包方向监理工程师提交了施工进度计划,如图2-1所示,该计划满足合同工期100天的要求。

在上述施工进度计划中,由于工作E和工作G共用一台塔吊(塔吊原计划在开工第25天后进场投入使用),必须顺序施工,使用的先后顺序不受限制(其他工作不使用塔吊)。

在施工过程中,由于业主要求变更设计图纸,使工作B停工10天(其他工作持续时间不变),监理工程师及时向承包方发出通知,要求承包方调整进度计划,以保证该工程按合同工期完工。

承包方提出的调整方案及附加要求如下。(以下各项费用数据均符合实际)

1.调整方案:将工作J的持续时间压缩5天。

2.费用补偿要求如下。

(1)工作J压缩5天,增加赶工费25000元。

(2)塔吊闲置15天,补偿:600元/天(塔吊租赁费)×15天=9000元。

(3)工作B停工10天造成其他有关机械闲置、人员窝工等综合损失45000元。

问题

如果在原计划中先安排工作E,后安排工作G施工,塔吊应安排在第几天(上班时刻)进场投入使用较为合理为什么