The()is a general description of the archi

题型:单项选择题

问题:

The()is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several(). In a workflow system, a process is specified using the process definition tool. Usually, processes are defined in terms of a(), which consists of()indicated using a circle, and()shown as a rectangle. These two components can be linked by means of a directed arc.

which consists of()indicated using a circle

A.positions

B.resources

C.conditions

D.places

考点:计算机软件水平考试高级系统分析师计算机水平考试高级系统分析师2008年上半年上午真题
题型:单项选择题

在《并购重组共性问题审核意见关注要点》中,报告书披露不存在现实同业竞争的,需要关注收购人或重组交易对方及其实际控制人是否进一步对避免潜在的同业竞争作出明确承诺。()

题型:单项选择题

患者,男性,50岁,咳嗽,咳痰史10多年,每年持续3月以上,活动后气急2年,病情加重3天,呼吸困难,查体:双肺叩诊过清音,听诊双肺干湿啰音。

示:胸片示:右肺中叶大片状实变影,血常规示:WBC:14.2×10/L,N:84%,心脏超声:右室流出道31mm。提问:目前作何诊断()

A.喘息型慢性支气管炎、肺气肿,急性发作期

B.肺炎

C.肺栓塞

D.慢性肺源性心脏病

E.心源性哮喘

F.肺癌

题型:单项选择题

扫描法也称时段定人法,即观察者(主要指教师)对班级全体幼儿平均分配时间,在相等的时间内对每个幼儿轮流进行扫描观察。()

题型:单项选择题

关于人力资本投资,表述正确的是( )。

A.成本在于产生人力资源

B.利益发生在现期

C.重点在未来的导向性

D.不需要初始投资

题型:单项选择题

某工程的总时差为3天,自由时差为1天,由于非承包商的原因,使该工作的实际完成时间比最早完工时间延迟了5天,则承包商可索赔的工期最多是()。

A.1天

B.2天

C.3天

D.4天