The project manager has just received a change from the customer that does not affect the project schedule and is easy to complete.What should the project manager do FIRST ?()
A.Make the change happen as soon as possibl
B.Contact the project sponsor for permissio
C.Go to the change control boar
D.Evaluate the other components of the“triple constraint”.