Project Time Management includes the proce
题型:单项选择题
问题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. ______ is following the process - Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities