Your project team identified six related projects with major dependencies on your deliverables. Some of these projects have a very similar scope and may overlap with your deliverables. In Light of this, which of the following should you be MOST concerned about
A) Scope change control.
B) Scope verification.
C) Risk response planning.
D) Communications planning.