问题:
As one of the tools and techniques of activity sequencing, a lead ______ .
A.directs a delay in the successor activity
B.could be accomplished by a finish to-start relationship with a delay time
C.means the successor activity cannot start until after the predecessor is completed
D.allows an acceleration of the successor activity