You are running a project for a customer based on a cost reimbursable contract with the following terms: Target costs, $1000000; fix fee, 100000; benefit/cost sharing, 80/20; price ceiling, 1200000. Which is the PTA (point of total assumption, break point)of the project ?()
A.$1300000
B.$1500000
C.$80000
D.$1125000