某工程项目的进度计划如下列双代号网络计划图所示,其关键线路是() A.①—②—⑥—⑧ 发布时间:2017-05-25 02:34 │ 来源:www.tikuol.com 题型:单项选择题 问题: 某工程项目的进度计划如下列双代号网络计划图所示,其关键线路是()A.①—②—⑥—⑧ B.①—④—⑤—⑧ C.①—②—④—⑤—⑥—⑧ D.①—③—④—⑤—⑦—⑧