A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ______.
A.change the scope baseline
B.call a meeting of the configuration control board
C.assign change tasks to project members
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline